WORK has begun on the next stage of a project to restore a Grade II* listed lido building back to its former glory.

The project, which has been led by Saltdean Lido Community Interest Company (SLCIC), will repair the crumbling structure and “bring new life to the derelict building” as a hub for the community.

The Save Saltdean Lido Campaign was set up in March 2010 by people in the area after plans were announced to fill in the swimming pool, develop the site extensively and create 102 flats on the historic lido.

The 40 metre pool tank was tackled first and reopened in 2017, attracting nearly 40,000 visitors in the first year.

The lido building is the current project, with Buxton Building Contractors being awarded the contract for the main section of work.

Buxton’s section of work should be completed by early 2023, while landscaping and finishing touches will see the site completed by the middle of 2023.

Derek Leaver, chairman of SLCIC, said: “Although demolition work started inside the building in November, it’s great to finally have scaffolding going up so people can see and believe that this project is really underway at long last.

The Argus: The old stairwell has been removed to allow light to flood in. The stage from the 1960s will be removed soonThe old stairwell has been removed to allow light to flood in. The stage from the 1960s will be removed soon

“Many people, and not just local residents, are thrilled that this unique building is not only being saved architecturally, but also being given new life and brought back into use.”

The group redesigned plans for the £7.5 million project in 2019, with the priority to maintain the historic elements of the 1938 building while also ensuring it met modern building regulations.

The building will feature various meeting rooms, a bar, coffee lounge, restored library, heritage learning zone and lots of space for activities. The aim is to return it to its former glory and allow the building and pool to work in tandem again.

The Argus: The new stairwell will connect up all levels of the Lido againThe new stairwell will connect up all levels of the Lido again

Part of this work to connect it all up is to restore the spiral staircase which was blocked off years ago. The staircase will act as a centre piece to the building and connect up all the “decks” and add to the cruise ship-like feel.

The ballroom on the first floor will be opened up, allowing light to flood into the open plan space, which will be available for event hire.

The project has also involved the National Lottery Fund, Brighton and Hove City Council’s heritage team and Historic England.

Derek added: “Starting construction is a milestone achievement following years of trying to get this over line. Three years ago we took a fresh look at the funding we had in place and the building plans and decided to redesign the whole project.

“The last 18 months has involved local architects, structural engineers, and other professional and we now have a better scheme allows us to restore the entire building and which gives us more space for community use and a gym in addition to a magnificent ballroom for hire for weddings and events.”

Have you got a story for us? Email news@theargus.co.uk or contact us here.

Follow us on FacebookTwitter and Instagram to keep up with all the latest news.

Sign up to our newsletter to get updates sent straight to your inbox.

You can also call us on 01273 021 400.